Emergency Response: Identifying and Mitigating Petroleum Vapor Intrusion at an Active Gasoline Station

Nottingham, Maryland

Two ARM Group field technicians examining soil cores on-site during petroleum vapor intrusion investigation.

ARM Group managed an investigation at an active gasoline station in Nottingham, Maryland, following the detection of petroleum vapors inside the onsite building. The multi-phase investigation, approved by the Maryland Department of the Environment (MDE), was part of an ongoing effort to ensure regulatory compliance and protect environmental and public health.


The Challenge

In October 2024, ARM was contacted late on a Sunday night by the client regarding employee complaints of odors inside the building. Within 12 hours of ARM collecting a sub-slab vapor sample, laboratory results confirmed the detection of volatile organic compound (VOC) concentrations linked to petroleum products. ARM immediately worked to mitigate vapors and restore safe conditions for the employees while maintaining compliance with MDE regulations.

The Solution

Over the following months, ARM worked closely with the client and MDE to implement remedial measures to prevent continued vapor intrusion.


To evaluate subsurface conditions, ARM developed an investigation plan, which included:

  • Installation and sampling of indoor and outdoor vapor monitoring points and sampling of indoor air.
  • Installation and sampling of nine monitoring wells to assess soil and groundwater conditions.
  • Use of sonic drilling technology to minimize surface disruption while improving sampling efficiency.
  • Real-time data analysis to guide remediation strategies.
  • Regulatory coordination with MDE to ensure compliance and site safety.


The subsurface investigation was implemented in March 2025. 


The Outcome

The remediation efforts allowed the gasoline station to resume operations within a timely manner with MDE approval. Following data analysis, ARM will develop a long-term monitoring and corrective action plan based on investigation findings, ensuring continued compliance and environmental safety.


Key Services Provide:

  • Emergency Response & Vapor Intrusion Mitigation
  • Regulatory Compliance & Agency Coordination
  • Subsurface Investigation & Groundwater Assessment
  • Sonic Drilling for Minimal Site Disruption
  • Remediation Planning & Monitoring

ARM Group has a proven track record of emergency response success, delivering Precise. Responsive. Solutions. that help clients maintain operations while addressing environmental challenges.


Click here to learn more about our environmental & emergency response services.

  • Prepared soil core samples laid out for review alongside field notebook during environmental site assessment.

    Slide title

    Field equipment and safety perimeter set up in gas station parking lot for vapor intrusion mitigation work.

    Button
  • Prepared soil core samples laid out for review alongside field notebook during environmental site assessment.

    Slide title

    Prepared soil core samples laid out for review alongside field notebook during environmental site assessment.

    Button
ARM Group Named to ENR’s Top 200 Environmental Firms
October 13, 2026
ARM Group earns recognition among ENR’s Top 200 Environmental Firms for its environmental consulting, engineering, and permitting solutions.
ARM Group Enterprises Ranks Number 12 on CPBJ’s Growth List
October 12, 2026
ARM Group Enterprises ranks number 12 among Central Penn Business Journal’s Fastest Growing Companies. Learn more about this recognition.
Environmental Planning for Data Centers
September 22, 2026
ARM Group helps clients move data center projects forward with confidence by bringing environmental scientists, engineers, geologists, surveyors, and permitting specialists together early in the development process.
Regulatory Trends Developers Should Watch in MD and VA
September 3, 2026
Planning a data center project in Maryland or Virginia? Connect with ARM Group early to evaluate regulatory considerations, permitting requirements, infrastructure needs, and site constraints before they impact your schedule.
Data Center Development in Pennsylvania
July 14, 2026
Pennsylvania data center development is evolving. Learn how early due diligence, permitting, and site planning can reduce risk and keep projects on track.
ARM Group & Batricity Partner on Battery Energy Storage Solutions (BESS)
April 22, 2026
ARM Group and Batricity partner to deliver turnkey battery energy storage (BESS) solutions, supporting grid resiliency, renewable integration, and energy optimization.
People Behind The Projects | ARM Group | Kyle ohnson
December 19, 2025
Get to know Kyle Johnson, PE, in ARM Group’s People Behind the Projects series—highlighting his engineering expertise and project leadership.
Energy Infrastructure Upgrades: Smarter Solutions for Natural Gas & Next-Gen Projects
October 10, 2025
Optimize your natural gas, cogeneration, SMR, and fuel cell projects with ARM Group. We provide siting, permitting, engineering, and interconnection expertise.
Accelerating Renewable Energy Projects: How to Overcome Siting, Permitting, and Grid Challenges
September 19, 2025
Accelerate your solar, wind, hydropower, and geothermal projects with ARM Group’s end-to-end expertise. From permitting to grid interconnection, we help renewable energy developers reduce risk and meet milestones.
 gravity meter surey by ARM Group
August 8, 2025
ARM Group’s Gravity Meter Reveals What’s Hidden Below the Surface Discover how ARM’s advanced gravity survey technology uncovers voids, faults, and hidden subsurface features before you build. Non-invasive, efficient, and risk-reducing, our Gravity Meter gives you critical clarity underground.
More Posts